Uaru Field FDP Review, Guyana
Performed in-depth review of the FDP which included assessments of:
- The strategy and the development model, as well as the criteria utilised in the Licensee choices including cost effectiveness and potential alternatives.
- The geological and geophysical interpretations, models, volumetrics and associated uncertainties assessed for individual reservoirs and at the field level.
- The production simulations and estimation of hydrocarbons to be produced, including recovery efficiency analysis, taking into consideration the use of natural gas for injection and export.
- An audit of the proposed project cost - development and production – and the project schedule, including tail end production.
- The proposed subsea system.
- The well & reservoir management including well design and production technology, and depletion strategy, taking into consideration of the GOG’s objective of maximising the recovery of hydrocarbon resources and no-gas flared.
- The proposed FPSO design and topside facilities.
- The Licensee’s plan to ensure the most efficient and beneficial use of the petroleum resources.
- The associated financial models, economic analyses and cost estimates and reports submitted by the Licensee towards ensuring financial optimization of oil and gas recovery profiles.
- The Decommissioning Plan and Budget.
- The natural gas utilization plan for the field.
- The overall risk management strategy.
- The incorporation of the lessons learnt from previous FDPs and related studies by the Licensee, as well as identifying how the Licensee(s) have addressed these findings in the context of a new FDP.
- Any revisions made to the FDP so as to ensure that the issues and deficiencies or requested modifications identified in the original FDP have been adequately addressed.
- How the Licensee has incorporated and can incorporate climate solutions into the proposed development